 ~ Challenges of SSP3 Construction
 
     
   



FAST FACTS

Concession Build, Operate and Transfer Scheme (BOT)
  Component
  • Regulating dam over Sungai Selangor at 66.5 Km of KKB - Bukit Fraser Road
  • Water treatment plants
    • 250 Mld intake and treatment works (125 Mld x 2) at Rasa to serve Northern Selangor
    • 800 Mld intake and treatment works (400 Mld x 2) at Bukit Badong to serve the Federal Territory
  • Realignment of a 7.7 Km section of KKB-Bukit Fraser Road
Dam Storage Capacity
  • 235 million cubic metres
Location
  • 5 Km east of Kuala Kubu Bharu, along Km 66.5 of Jalan KKB-Bukit Fraser
Height
  • 110 meters
Type
  • Rock filled
Width
  • 800 meters
Catchment area
  • 197 sq km mainly secondary jungle
Impoundment
  • 600 hectares/ 6 sq km (3% of catchment area)
Construction Period Regulating Dam
  • 3 years
Water Treatment Plant
  • In stages over 66 months
Project Consultants
(SPLASH Appointed)
  • SMHB Sdn Bhd
  • Angkasa GHD
  • Universiti Kebangsaan Malaysia (UKM)
  • Setia Sepakat Perunding (SSP)
  • Garis Architects
Project Consultants
(Government Appointed)
  • KLIAB
  • Gunung Ganang


Note: Click the picture to enlarge