Sungai Selangor Water Supply Scheme Phase 3 (SSP3) is progressing smoothly and according to schedule. Construction commenced in March and to date construction is at the following stages:
|
| Package 1A: |
|
Scope of works:
- Construction of approximately 7.8 Km of road realignment to replace a stretch of KKB-Bukit Fraser Road that will be flooded.
- Construction of 2 bridges:
- Bridge over Sg Selangor
- Bridge over Sg. Luit
|
Completion Date :
Opened to Public :
Handed Over to Government :
|
10 September 2001
24 September 2001
5 November 2002
|
Package 1B:
|
|
Scope of work:
- Construction of approximately 400 m diversion
tunnel, 110m high and 800m wide earth core rockfill dam
|
| Completion Date : |
April 2003 |
|
Scope of work:
- Construction of 41 houses, community
facilities and amenities for Kg Gerachi
|
| Status : |
Completed and relocated Orang Asli to the new village in June 2001. |
| |
|
Scope of work:
- Construction of 43 houses, community
facilities and amenities for Kg Pertak
|
|
Status : |
Completed and relocated to the new village in March 2002 |
Scope of work:
Status :Completed and handed over to IKBN on 1 July 2002
|
Package 2 & 4:
|
|
Scope of works:
- Construction of new raw water intake structure and pumping station at Rasa
- Construction of new water treatment plant with a capacity of 250MLD in 2 stages at 125mld each
- Construction of 32ML R.C balancing
reservoir at Rasa
|
|
Status :
(Stage 1) :
(Stage 2) : |
Completed and operational effective 23 Nov 2001
Completed and operational effective 23 Jan 2004 |
Package 3 & 5: |
|
Scope of works:
- Construction of new raw water intake structure and pumping station at Batang Berjuntai
- Construction of new water treatment plant with a capacity of 800MLD in 2 stages at 400MLD each
- Construction of 82ML R.C balancing
reservoir at Bukit Tadun
|
|
Status :
(Stage 1) :
(Stage 2 - May 04) : |
Completed and operational effective 23 July 2003
56.28% |