PROJECT PROGRESS

Sungai Selangor Water Supply Scheme Phase 3 (SSP3) is progressing smoothly and according to schedule. Construction commenced in March and to date construction is at the following stages:


Package 1A: Realignment of KKB-Bukit Fraser Road

Scope of works:
  • Construction of approximately 7.8 Km of road realignment to replace a stretch of KKB-Bukit Fraser Road that will be flooded.
  • Construction of 2 bridges:
    • Bridge over Sg Selangor
    • Bridge over Sg. Luit
Completion Date :
Opened to Public :
Handed Over to Government :
10 September 2001
24 September 2001
5 November 2002



Package 1B:



Sungai Selangor Dam

Scope of work:
  • Construction of approximately 400 m diversion tunnel, 110m high and 800m wide earth core rockfill dam
Completion Date : April 2003


Kg Gerachi Resettlement

Scope of work:
  • Construction of 41 houses, community facilities and amenities for Kg Gerachi
Status : Completed and relocated Orang Asli to the new village in June 2001.


Kg Pertak Resettlement

Scope of work:
  • Construction of 43 houses, community facilities and amenities for Kg Pertak
Status      : Completed and relocated to the new village in March 2002


Institut Kemahiran Belia Negara

Scope of work:
  • Relocation of IKBN
Status      :Completed and handed over to IKBN on 1 July 2002



Package 2 & 4:



Rasa Water Treatment Plant

Scope of works:
  • Construction of new raw water intake structure and pumping station at Rasa
  • Construction of new water treatment plant with a capacity of 250MLD in 2 stages at 125mld each
  • Construction of 32ML R.C balancing reservoir at Rasa
Status   :
(Stage 1) :

(Stage 2) :

Completed and operational effective 23 Nov 2001
Completed and operational effective 23 Jan 2004



Package 3 & 5:



Bukit Badong Water Treatment Plant

Scope of works:
  • Construction of new raw water intake structure and pumping station at Batang Berjuntai
  • Construction of new water treatment plant with a capacity of 800MLD in 2 stages at 400MLD each
  • Construction of 82ML R.C balancing reservoir at Bukit Tadun
Status   :
(Stage 1) :

(Stage 2 - May 04) :

Completed and operational effective 23 July 2003
56.28%