 ~ Challenges of SSP3 Construction
 
     
   



Schedule of Completion for SSP3 Components


Project Details
Package 1A
  • Re-alignment of Federal Route 55 (Kuala Kubu Bharu-Frasers Hill road)
  • Completed: 2001
  • Handed to Federal Government : November 2002
Package 1B
  • Sungai Selangor Dam - Completed: April 2003
    Full Impoundment: April 2004
  • IKBN - Completed: June 2002
  • Kg. Peretak - Completed: November 2001
  • Kg. Gerachi - Completed: April 2001
Package 2
  • Rasa Water Treatment Plant (Phase 1)
  • Completed: Nov. 2001 - capacity: 125Mld
Package 3
  • Bukit Badong Water Treatment Plant (Phase 1)
  • Completed: July 2003 - Capacity: 400 Mld
Package 4
  • Rasa Water Treatment Plant (Phase 2)
  • Completed: Jan 2004 - Capacity: 125 Mld
Package 5
  • Bukit Badong Water Treatment Plant (Phase 2)
  • Expected Completion: July 2005 - Capacity: 400 Mld