DOE approves EIA report and sets conditions for implementation |
|
|
| |
|
 |
|
|
| |
|
Selangor State Govt approves project to proceed, subject to compliance with conditions of EIA approval. |
|
|
 |
| Implementation Committee set up by the State Government to monitor implementation of the project and compliance to EIA approval conditions. |
|
|
|
Project proponent hires Enviromental Management consultant to draw up Environmental Mgt Plan (EMP) |
 |
|
|
|
 |
| Committee appoints independent EIA consultant to monitor implementation of EMP Plan |
|
DOE reviews and approves EMP |
|
 |
|
 |
|
| Full time officer from the independent EIA consultant to monitor the implementation |
|
Full time DOE officer to monitor implementation of EIA approval conditions |
|
Full time Enviromental Management Officer from Project proponent's consultant to monitor implementation |
 |
|
 |
|
 |
Implementation of EIA Conditions (By contractor) |